Recent Projects
Home ] Group company profile ] Company Facilities ] Computer Design ] Contacts ] Location Map ] Picture Gallery ]

 

 

Up
Atrium
Holiday Inn

 

Some  Recent project completed by Darke Tech are :-

Atrium Birmingham for Six Continents
Holiday Inn - Canopy for Fitzpatrick

Please Select the required link -  left  - for  further pictures of the project.

Atrium Birmingham - Developed the Design and Built by Darketech

View of main Atrium showing Stairs and Balustrade - Please select for enlarged view
The elliptical main stair cores shown in the pictures are of a mild steel construction each weighing 7 tonnes. 
Balustrades are stainless steel with timber treads and hand rails.  Each completed stair cost approximately £100,000.
Hand rail design sections & construction - Please select for enlarged view Core section design & construction - Please select for enlarged view
Due to the complexity of the core shapes (illustrated in the drawings) and the need for extreme accuracy and a high standard of finish, the cores were prefabricated at the Stilton works. They were then transported to Birmingham. As each core was approximately 12 Metres x 3.6 Metres and a "Notifiable Load", police designated a route into Birmingham City Centre. Fleet Street was closed for the operation.
Atrium_Staircase core section stairs - Please select for enlarged view

Whilst "Developing the Design" the 7 tonne cores were superimposed onto the client’s CAD drawings to ensure that we could get them into the building in one piece.

We agreed a route through a large window, but then had to design and build two temporary cranes inside the building to move the structures to their final position in the Atrium.

Developed the Design and Engineered by 
Tony Darke (MD) D & B Darke Group.
Once the cores were upright, we then used the same cranes to winch the 2.5 tonne prefabricated landings into position.
 Holiday Inn Canopy
Each Canopy cost approximately £20,000.The completed canopy  was prefabricated at our Stilton Works and transported for erection  to the Holiday Inn site - Cambridge. A large mobile crane was hired to lift the sections and the large toughened glass panels into position. 
Developed the Design and  Engineered by Paul Newall Project manager of Darke Tech Ltd.
On-Site chief David, supervising  final erection sequence. - Please select for enlarged view
Prefabrication at Stilton Works - Please select for enlarged view Canopy section design & construction - Please select for enlarged view

Goto top of file

All slides are courtesy of Darke Tech Ltd and the relevant clients.